Arrow Ceilings took on a Full Shop Fit out on behalf of Hurst Interiors.

Central England Coop Funeral Lowestoft had a short three programme.
The 55m² area had severe Damp through out the building, on the exterior and party walls and especially the previous Toilet at the back of the Building.

We had our SMSTS Site Manager on site through the job from Site Set-up to Hand-over, Overseeing all tasks and ensuring all Site Paperwork and Health and Safety was complete and in place.

We also had our Joiner on site carrying out tasks including:

- Damp Proofing and Vapour Membraning the entire building
- Installing Timber framing for all internals walls
- Insulating the Timber Framing and Plaster boarding
- Installing Timber Partitions, Forming the layout of the shop
- Forming DDA Compliant WC
- Fitting two Internal Doors and a Sliding Door
- Fitting all Wall Finishes, Skirting and Architraves
- Fitting all Door Finishes, Handles, Kick plates, Hooks and so on,
- Designing and Installing a Mains Cupboard and access
- Installing Furniture, including Shelves and mirrors and so on
- Installing a Work station, a desk and cabinets
- Installing a Kitchen worktop and units above and below

The Electricians installed new mains power to the building pre start,
then as per programmes completed First Fix and enable other trades
Returned to site to complete Second and Final fix.


Plumbers on site installed new DDA with a Saniflow System, they then removed the previous toilet and plumbed the Kitchen sink and waste.


Decorators had two days on site and completed a exterior revamp with the Brickwork, Soffit and Fascia and Widow Frames being painted and then the interior wall had been Taped and filled, caulked and the decorated.
Matt Finish is the main areas, Eggshell in the DDA toilet, and High Gloss on the Wall Finishes.

We then had our Suspended Ceiling Fitters on site and they installed four ceilings of AMF Ventatec 24mm White Grid work with a British Gypsum Satin Spa 600mm x 600mm ceiling tile.

The Carpet Fitter came and installed the Main area carpet, the DDA Coved Skirting and Vinyl flooring and the Main Entrance had a door well.

We managed to keep on track with the short and squeezed, tight programme. Handing over to a Happy Client and a Happy Store Manager, smiling with her new Ready to Open Store.

Send Us A Message

***
This form collects your details so that we can process your enquiry. View our privacy policy to see how we protect and manage your data.
Cookies

This website uses cookies. Please let us know if you agree to the use of these cookies :
I Accept I Decline

3rd Party Data Processors | Disable Cookies
Cookies